© Copyright 2025
Tarek and El-Salam Gas Fields
Pipeline, Piping Systems, and Steel Structures
Western Desert, Egypt
Tarek and El-Salam Gas Fields
Pipeline, Piping Systems, and Steel Structures
Western Desert, Egypt
Project
Tarek and El-Salam Gas Fields
Pipeline, Piping Systems, and Steel Structures
Location
Western Desert, Egypt
Description
The project involved the installation of a pipeline designed to collect gas from the wellhead and transport it to the gas collection station. The scope of work encompassed all mechanical and civil operations related to the pipeline, including cold cutting and the modification of tie-in points.
The pipeline was constructed using stainless duplex steel, and all welded joints were completed using the GTAW welding process by our qualified team.
The project also included the welding, inspection, testing, and installation of a total of 18,000 diametric inches of piping systems, made from duplex steel, carbon steel, and stainless steel.
Additionally, a large steel-structured pipe rack was built by our experienced workforce to accommodate the pipes, with all operations executed onsite.
Owner
Khalda Petroleum Company
Completion
1997
Project
Tarek and El-Salam Gas Fields
Pipeline, Piping Systems, and Steel Structures
Location
Western Desert, Egypt
Description
The project involved the installation of a pipeline designed to collect gas from the wellhead and transport it to the gas collection station. The scope of work encompassed all mechanical and civil operations related to the pipeline, including cold cutting and the modification of tie-in points.
The pipeline was constructed using stainless duplex steel, and all welded joints were completed using the GTAW welding process by our qualified team.
The project also included the welding, inspection, testing, and installation of a total of 18,000 diametric inches of piping systems, made from duplex steel, carbon steel, and stainless steel.
Additionally, a large steel-structured pipe rack was built by our experienced workforce to accommodate the pipes, with all operations executed onsite.
Owner
Khalda Petroleum Company
Completion
1997